St. Tammany Parish Hospital Addition and Renovations
An 11-phase approach was taken to the multi-faceted interior renovation and addition scope of this hospital project. Woodward developed a highly technical sequence of work to minimize disruptions to both patients and providers through construction.
Woodward served as general contractor on this four-phase renovation and addition on an operating hospital campus. The project scope included interior renovations to the kitchen and dining areas, Operating Room shell, post-anesthesia care unit, and the neonatal intensive care unit. Also in the scope were buildouts for a new family center and new sterilization suite.
A new two-story, 11,000sf addition to the support services building was also part of the project scope. Woodward is proud to note that the project progressed on time and within budget.
“We appreciate the level of professionalism by your team onsite, and the care they put into performing major construction on an operating campus.”